Project Overview
  • Project Azure

  • Builder Iurada Property Group

  • Architect Interlandi Mantesso

  • Location Hampton, Victoria

  • Framing Used Top Level Wall & Roof Truss Framing

THE PROJECT CHALLENGE / Develop a faster and easier to install system for the top level structure while still complying with the required building regulations.

 

THE SBS STEEL SOLUTION /
> The lightweight alternative replaced substantial structural steel and was engineered to support the roof plan platform.
> Fire rating allowances were accommodated within the SBS Group design, satisfying the FRL (fire resistant level) in accordance with AS 1530.
> Using the latest BIM modelling 3D technology, framing was detailed and fabricated to millimetre perfect accuracy.
> SBS Group facilitated an on site coordination meeting with the installer, site manager and project manager to ensure an efficient and streamlined install.
> The speed of erection was a key advantage of using steel, eliminating unnecessary fixings/brackets with no further straightening required once frames were installed.

 

TOTAL L/M OF STEEL FRAME SUPPLIED / 5787

 

TOTAL M2 OF SBS GROUP FOOTPRINT AREA / 417.82

 

FLOOR COUNT / 3